How long does a kitchen remodel take, and where do you live in the meantime?

A realistic phase-by-phase kitchen remodel timeline for Scottsdale and Cave Creek homes, what causes delays, how to set up a temporary kitchen, and what snowbirds should plan before leaving mid-project.

Reading
3 minutes
Kitchen in mid-remodel with base cabinets installed and a temporary kitchen set up in an adjoining room

The short answer

Design and ordering take longer than construction. The demolition week is the shortest part of the schedule.

Phases: design, ordering, construction, finishing
4
Cabinets, stone and appliances set the real schedule
Lead time
Temporary kitchen setup saves weeks of takeout
1
Complete drawings before bids prevent most delays
Drawings

Where does the time actually go?

Most of the calendar is spent before anyone picks up a hammer. Design decisions, permit review and material lead times take the longest. Custom cabinets and stone slabs can take weeks or months to arrive, and a missing appliance can hold up the whole job.

In Scottsdale, summer is a good time to plan, because many homeowners are away and trades have more availability. Cave Creek and Carefree homeowners who are full-time residents should plan for the long driveway logistics in the post on septic, well and propane considerations.

The four phases

PhaseWhat happensWhat can slow it down
Design and drawingsLayout, finishes, appliances, drawingsLate decisions, changing appliances
Permits and orderingCity review, orders placedReview comments, long lead times
ConstructionDemo, rough-in, cabinets, counters, finishHidden conditions, inspection scheduling
FinishingPunch list, paint touch-up, cleaningDamaged or missing items

Durations vary widely by scope and lead times. Ask your designer and contractor for a written schedule.

Four ways to live through a remodel

Pick your setup before demolition day, not after.

  1. 01

    Temporary kitchen in another room

    Arizona fit: 5 out of 5
    Best for
    Families staying home during the remodel
    Why it works
    A fridge, microwave, hot plate and a folding table in the dining room or garage covers most meals.
    Watch out
    Keep it away from dust. Seal the construction zone.
  2. 02

    Outdoor kitchen as the temporary kitchen

    Arizona fit: 3 out of 5
    Best for
    Homes that already have a built-in grill
    Why it works
    Winter and spring evenings make an outdoor kitchen a workable solution.
    Watch out
    Not practical in July. Plan for the season.
  3. 03

    Stay in a guest suite or casita

    Arizona fit: 4 out of 5
    Best for
    Properties with a second living space
    Why it works
    Separates you from dust and noise.
    Watch out
    Check that the casita has its own cooling and a place to cook.
  4. 04

    Move out for the messy weeks

    Arizona fit: 3 out of 5
    Best for
    Full remodels with structural work
    Why it works
    Demolition and rough-in are the loudest phases, and some households choose to be away.
    Watch out
    Plan pet and mail arrangements. Keep a key and a contact.

Do it yourself

DIY: set up a temporary kitchen in one afternoon

A simple setup makes the whole project easier on the household.

Time
2–3 hours
Cost
$50–$150

You will need

  • Folding table
  • Mini fridge or your old fridge
  • Microwave
  • Hot plate or toaster oven
  • Dish tub
  • Plastic bins
  1. Choose a room near water

    A laundry room or bathroom sink works for washing up.

  2. Set up the appliances

    Use dedicated outlets and avoid overloading a circuit.

  3. Pack the pantry into bins

    Keep only the items you will use.

  4. Seal off the work zone

    Use plastic sheeting and tape at doorways, and cover vents.

Do you need drawings before bids?

Yes, for anything more than a refresh. Drawings let every contractor price the same job, and they surface problems on paper rather than on site. Our guide to residential drafting services explains what to expect. When opening a wall is part of the plan, our post on removing a wall in a Scottsdale home covers the questions to settle first.

What does it cost to remodel a kitchen and open the wall to the living room? It depends on scope, structure and finishes. We don’t quote a number here, because it would mislead. Ask for itemized bids built from the same drawings, and you’ll be able to compare them. See our kitchen and bath design services for how we scope projects.

Before you build

Check your own city's rules

Permits, zoning and setbacks are set by the city or town, and they change. Use these official pages to confirm what applies to your lot before you order materials or sign a contract.

01

Check paperwork you already have

Your parcel number (APN) is printed on your county property tax statement and usually on your deed or title documents.

02

Or search by address

The Maricopa County Assessor lets you search by street address or owner name and returns the parcel number.

03

Use it on the city tools

Scottsdale, Phoenix and Cave Creek map and permit tools accept an address, and many also accept a parcel number.

Find your parcel number(Maricopa County Assessor, opens in a new tab)

These are links to official government sites, not advice. Requirements depend on your lot, zoning and the scope of work, so confirm with the city or town and your designer before you start.

Where it matters

  • Scottsdale

    Many Old Town and McCormick Ranch homeowners plan remodels for the summer months when trades have more availability.

  • Cave Creek

    Long drives and rural utilities add steps to the schedule. Plan deliveries and utilities early.

  • Phoenix

    Arcadia and Biltmore remodels often involve older homes where hidden conditions add time.

FAQ

Questions, answered

How long does a kitchen remodel take in Scottsdale?

Longer than most people expect, because design, permits and lead times come first. Ask your contractor for a written schedule that separates each phase.

Where should I live while the kitchen is being remodeled?

Most families set up a temporary kitchen in another room. If you have a casita or guest suite, that works well too.

Do I need drawings or a designer before I get contractor bids?

For anything beyond a refresh, yes. Drawings let every contractor price the same scope.

What should a snowbird plan for before leaving mid-remodel?

Agree in writing on access, approvals and progress updates, and arrange for dated photos.

What does it cost to remodel a kitchen and open the wall to the living room?

It depends on scope, structure and finishes. Get itemized bids built from the same drawings.